Member of the
Cooling Technology Institute
Cooling Tower Technology Institute Logo
Company Overview | Performance Metrics | Know Your Objectives | Diagnostic Performance Advantage | Consultant Profile
Diagnostic Performance Audit™ | Thermal Capability Status Test | Cooling Tower Upgrade or Capital Cost Avoidance | Film Fill Fouling Monitoring | Cooling Tower Bid Assistance | Seminars
Overseas Refinery | North American Refinery | Air Separation Plant
Site Engagements | Customer Testimonials

Overseas Refinery Case Study

Cooling Tower Testing - DCS small logo

Cooling Tower Diagnostic Performance Audit™ Saves Plant $6 Million

During planning stages of a recent oil refinery turnaround, plant management confirmed that current production levels would only meet their contractual obligations and local market demands. However, they also recognized that their facility was cooling limited and unable to produce excess inventory to cover the shutdown period. This problem was exacerbated by the refinery's remote location. Management was faced with a $6 million dollar contingency plan to ship in refined product by ocean-going tankers.

Hoping to avoid the costly contingency, a cooling tower Diagnostic Performance Audit™ was commissioned to uncover the cause of the cooling tower's poor performance. Day one preliminary testing revealed some initial positive results - a possible fan stall condition. Following up on this discovery, more focused diagnostic tests were conducted to verify and probe deeper into the surprise results.

In the final analysis, specific problems were positively identified and the issued audit report recommended a list of 6 Targeted Corrective Actions (TCA). Refinery management were then able to schedule the TCA's to restore cooling tower performance with minimal cost and disruption to operations. After implementing only the first TCA, sufficient cooling capacity was recovered to increase process throughput to provide inventory for the planned shutdown.

By leveraging the techniques and analyses of a cooling tower Diagnostic Performance Audit™, the out-sourcing contingency and its estimated $6 million costs were avoided. This amount does not account for any cost savings accruing from the ongoing improvement in operating efficiency.

Cooling Tower Testing - DCS small D logo | Legal | Email | ©2004 - 2006 Diagnostic Cooling Solutions